Kuhnel Garden Railroad
(Wabash and G)
Construction of the Kuhnel Garden Railroad began in August 2003. In a 30' x 60' section of slightly sloping land, work began with clearing out some old stumps, and a couple of small trees. Then 160 railroad ties were cut in half and placed on end, buried about 2', and joined together by reinforcing rod and pressure treated 2x4s. About 150 cubic yards of fill were brought in.
The photos below show progress to-date (November 2004). The walls are done and the fill is all in and compacted. The mountains, tunnel, and rock work will commence soon. Track laying on the east side is nearly complete, including ballast, along with the planting of 120 heather plants. A pond has been roughed in, and a tunnel placed. Rockwork and trestle work will begin soon on the mountain (east) section. The driving of the golden spike is targeted for the Spring of 2005
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|